2" of foam, 1/2" rebar on 24" centers, about 1000ft of per, 12 yards of 4500psi concrete with fibers added to get a 4" thick . It's a floor.
The pour was easy, 1st truck went to the back, second to the front, very little manual work. We floated it.....then the rain came. We got about 2" in 5-6 hours.....it was supposed to miss us and go north but I bought a big tarp just in case. The first attempt at a tart tent was a disaster but 2nd attempt worked pretty well and we were able to keep the floor pretty dry and get it finished....but it was about a 14 hour day, mostly in the cold rain.
The lumber was delivered today, framing over the holiday weekend weather permitting
Attachments: |
20171117_074350-resized-1024.jpg [ 427.39 KiB | Viewed 11588 times ]
|
20171117_122124-resized-1024.jpg [ 346.05 KiB | Viewed 11588 times ]
|
20171117_203745-resized-1024.jpg [ 262.22 KiB | Viewed 11588 times ]
|
20171118_081725-resized-1024.jpg [ 424.09 KiB | Viewed 11588 times ]
|
20171118_152654-resized-1024.jpg [ 270.75 KiB | Viewed 11588 times ]
|
20171118_152726-resized-1024.jpg [ 271.34 KiB | Viewed 11588 times ]
|
20171119_143901-resized-1024.jpg [ 394.55 KiB | Viewed 11588 times ]
|
|